Y
YLE
Hi,
I heard already reading thru the posted messages that MSP is not the cost
managing application but still decided to ask. I was asked to investigate the
possibility to use MSP to track Project Commitments. The amounts that are
committed to be spent (as part of the base line cost). For example Material
Order contracts. It will be paid according to the set up plan and project
development. I need to have ability to allocate the portion of the resource’s
work/cost as committed amount and possibly track them separately. Actual will
be updated manually against committed and additional (non-committed cost). I
believe I could do it thru custom cost fields but only at the task level
ignoring resources assigned to the task. For example the task with assigned
labor and material where material is committed amount and I have to track it
separately. Any suggestions???
Thanks for the help in advance
I heard already reading thru the posted messages that MSP is not the cost
managing application but still decided to ask. I was asked to investigate the
possibility to use MSP to track Project Commitments. The amounts that are
committed to be spent (as part of the base line cost). For example Material
Order contracts. It will be paid according to the set up plan and project
development. I need to have ability to allocate the portion of the resource’s
work/cost as committed amount and possibly track them separately. Actual will
be updated manually against committed and additional (non-committed cost). I
believe I could do it thru custom cost fields but only at the task level
ignoring resources assigned to the task. For example the task with assigned
labor and material where material is committed amount and I have to track it
separately. Any suggestions???
Thanks for the help in advance