A
A-Saleh
Hi,
For a given task; I assign three types of resources i.e. [Work, Material &
Cost]. Work and material resource rates are inserted in the [Resource Sheet],
moreover the cost of the [Cost] resource is also inserted in the [Task
Information]. Now, when updating the task to be 100% complete as scheduled; I
realize that the total [Actual Cost] of the task does not include the cost of
the [Cost] resource,…, However, when I assign [Cost] resource ONLY to a task
and update it as above, in this case the [Actual Cost] of the task does
include the cost of the [Cost] resource,.., is that normal behavior of the
Program?
Thanks in Advance
For a given task; I assign three types of resources i.e. [Work, Material &
Cost]. Work and material resource rates are inserted in the [Resource Sheet],
moreover the cost of the [Cost] resource is also inserted in the [Task
Information]. Now, when updating the task to be 100% complete as scheduled; I
realize that the total [Actual Cost] of the task does not include the cost of
the [Cost] resource,…, However, when I assign [Cost] resource ONLY to a task
and update it as above, in this case the [Actual Cost] of the task does
include the cost of the [Cost] resource,.., is that normal behavior of the
Program?
Thanks in Advance