J
Jon Smith
I have Project 2007 with SP1 and the Infrastructure update loaded (ref KB
951547). To try to isolate my problem, I have created a short project plan.
In my plan, I create task A. I also create Resource 1 that I have specified
as a Cost Resource.
I go into the Task Usage view and assign Resource 1 to Task A and enter
$4000 in the cost field on the day when I need to spend the 4K and then I
baseline the entire plan and Cost, Baseline Cost, and Remaining Cost all show
at $4000, so everythign is ok at this point.
I then go into the Task Usage and enter $2,000 into the Actual Cost field
for the same day (pretend I didn't spend it all on that day) and my cost goes
to $6,000, my remaining cost and baseline Cost stay at 4K and my cost
variance is zero. Why does my remaining cost not drop to 2K and my cost not
stay at 4K? If I were to change remaining cost to 4K, then I could see why
cost would now be 6K.
If I were to change the example to the corresponding Work fields along with
the resource, then the resource would show remaining work of 2 hours and work
would not change.
Any help is gratefully appreciated.
r/Jon
951547). To try to isolate my problem, I have created a short project plan.
In my plan, I create task A. I also create Resource 1 that I have specified
as a Cost Resource.
I go into the Task Usage view and assign Resource 1 to Task A and enter
$4000 in the cost field on the day when I need to spend the 4K and then I
baseline the entire plan and Cost, Baseline Cost, and Remaining Cost all show
at $4000, so everythign is ok at this point.
I then go into the Task Usage and enter $2,000 into the Actual Cost field
for the same day (pretend I didn't spend it all on that day) and my cost goes
to $6,000, my remaining cost and baseline Cost stay at 4K and my cost
variance is zero. Why does my remaining cost not drop to 2K and my cost not
stay at 4K? If I were to change remaining cost to 4K, then I could see why
cost would now be 6K.
If I were to change the example to the corresponding Work fields along with
the resource, then the resource would show remaining work of 2 hours and work
would not change.
Any help is gratefully appreciated.
r/Jon