Cost Rate Tables

G

George

Hi all,

Is there any way to have more than 5 tabs? and can you rename them
from A, B, C, etc to something more meaningful?

You see depending on the task the user undertakes the price will be
different (e.g. DB design, Coding, HTML design, flash animation dev,
etc).

From what i've seen the answer will be no, but I thought I would
double check.

Thanks for your time,
George.
 
D

Dale Howard [MVP]

George --

You are limited to five cost rates per resource and you cannot rename the
sheet tabs for the cost rate tables. To change the cost rate used for each
assignment, apply the Task Usage view, then temporarily insert the Cost Rate
Table column. By default, the rate for Cost Rate Table A is always used
when you initially make an assignment. After you have assigned resources to
a task, you can then change the Cost Rate Table for each assigned resource
in this view. Hope this helps.
 