GreuMorb
Hi.
I have a big problem using the new type of resource: Cost Resource.
If I assign a Cost Resource to an activity with long duration (> 60
days), after creating OLAP Cube, cost value of Cost Resource
assignement in Project Professional doesen't match with corresponding
cost value in the OLAP views. Even if it's not a big difference, it's
however a big problem! And it doesn't happen with the other type of
resources (Work and Material).
Is it a bug?
Thanks