When I assign a Cost Resource to a task, and it is the only resource
on the task, it works as expected in terms of Actual Cost accrual
being tied to % Complete.
When I assign an additional Work resource to the task, the Cost
Resrouce accural is no longer tied to the % Complete of the task,
though it is tied an assignment level % Work Complete for the task.
You can see that by adding % Work Complete to a Resource Usage view.
Is that by design or a bug?
Greg