cost spread in task usage view

  • Thread starter george.michael.mott
  • Start date
G

george.michael.mott

I have a schedule with that uses baseline and baseline 1 fields. When
I access task usage and make Work, Baseline Work and Baseline1 Work
available there are only values shown for work and baseline work.

any ideas?

Using MS project 2007 with SP2.

Thanks
 