Gosh. I replied with my recollection of what help said. That clearly is
a "bug" in Help.
Double clicking on a resource record you get the more detail input form.
on the "General" tab is where you specify the cost type. Pressing the
Help button there gives a bit more info:
"(cost resources: Resources that don't depend on the amount of work on a
task or the duration of a task, such as airfare or lodging.)".
To use, you create the cost type recourse, e.g. "airfare". May be other
places to do this, but if you double click on a task, go to the tab:
resources, you can assign this "airfare" resource to a task and give it
a cost, e.g. €450 or something. That value is added to the [Cost] field
by Project.
--rms
www.rmschneider.com
Mary said:
Thanks for your reply Rob. However, the Help only refers to Work and Material
type resources. It doesn't mention the Cost type.
.