count days

T

tsutton

How do I in the task bar remove nonworking days from the count numbers?
How do I in the task bar make the date the project starts 0?

Frinday September 1 = 0 (Start of project)
Saturday September 2 = n/a
SUnday September 3 = n/a
Monday September 4 = n/a (Holiday)
Tuesday September 5 = 1
Wednesday September 6 = 2
 
J

John

tsutton said:
How do I in the task bar remove nonworking days from the count numbers?
How do I in the task bar make the date the project starts 0?

Frinday September 1 = 0 (Start of project)
Saturday September 2 = n/a
SUnday September 3 = n/a
Monday September 4 = n/a (Holiday)
Tuesday September 5 = 1
Wednesday September 6 = 2

tsutton,
Well, you don't. The timescale can be set to start at "0" with time
periods numbered consecutively but Project does not have a timescale
option to "skip" now-working time. Non-working time can also be made to
appear in front of task bars effectively blocking non-working time out,
but to get exactly what you want you will need to export the data to
another application (e.g. Powerpoint, Excel, etc.) where there is more
flexibility with formatting.

Hope this helps.
John
Project MVP
 