R
Rick
I am working on a schedule for a construction project that is based on a
contract. The contractor has 30 calendar days to complete a portion of the
work
i.e. from September 15, 2008 to October 15, 2008.
When I enter September 15, 2008 into the calendar, the finish day comes up
October 24, 2008. should be October 15, 2008. I assume what is going on is
the working calendar thing and not including Sat and Sun, How do I get the
calendar to count all days for a particular task?
contract. The contractor has 30 calendar days to complete a portion of the
work
i.e. from September 15, 2008 to October 15, 2008.
When I enter September 15, 2008 into the calendar, the finish day comes up
October 24, 2008. should be October 15, 2008. I assume what is going on is
the working calendar thing and not including Sat and Sun, How do I get the
calendar to count all days for a particular task?