Please help: 'Change working time' does NOT change working time

Discussion in 'Project' started by E Colmenero, Feb 8, 2017.

  1. E Colmenero

    E Colmenero

    Joined:
    Feb 8, 2017
    Messages:
    1
    Likes Received:
    0
    I want to change an existing project from the standard calendar from the standard calendar to the 24 hrs calendar.
    Used 'Project', "Change working time" and selected calendar '24 hrs'. I see the hours in that dialog box change.
    But then when I click OK, my project is still on the Std calendar, and if I click on 'Change work time' again, I see the calendar has always been 'Standard'.

    Any idea why it won't change?

    Thanks a lot,
     
    E Colmenero, Feb 8, 2017
    #1
    1. Advertisements

  2. E Colmenero

    Scrappy33

    Joined:
    Mar 9, 2017
    Messages:
    4
    Likes Received:
    1
    I would try changing it in Project information too. If you cant do it that way, you could manually change the calendar in the Calendar Type field and fill down to the remaining tasks in the schedule. Let me know if that works.

    Justin
     
    Scrappy33, Mar 9, 2017
    #2
    1. Advertisements

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments (here). After that, you can post your question and our members will help you out.