S
Silvia
I want to set the duration of activities in a project of 4 years, entering
the actual duration in months. If I enter the duration in months and the
start date of the activity, the end does not match the actual length of
Calendar. Which option I must change in order fto obtain that the 6 months
scheduled are really 6 month and not working months (lasts 20 days?)
Ex.
Duration: 6months - start: 1 April 2008 - end: 15 September 2008 (what I get)
Duration: 6months- start: 1 April 2008 - end: 1 October 2008 (what I want: 6
months Real)
the actual duration in months. If I enter the duration in months and the
start date of the activity, the end does not match the actual length of
Calendar. Which option I must change in order fto obtain that the 6 months
scheduled are really 6 month and not working months (lasts 20 days?)
Ex.
Duration: 6months - start: 1 April 2008 - end: 15 September 2008 (what I get)
Duration: 6months- start: 1 April 2008 - end: 1 October 2008 (what I want: 6
months Real)