I am new to the project 2003.
I have one project schedule for the period of Jan 2008 - April 2008. The
actual Start and completion of the project was July 2008 - Sep 2008. When I
updating the actual duration, the total project schedule gets changed to the
actual duaration. But I need to show the scheduled and actual period in a
single chart. Kindly let me know the way to get the chart with Scheduled Vs
Actual