J
Jim Zeeb
I have an MsProject 2003 schedule. There is a Fixed Duration task that has a
Finish that is showing 3 months late. When I try to change the duration from
316d to 253d, it will not change.
All the resource assignments for this task are showing a Finish of 6/25/10,
but the Task Finish is showing 9/24/10. Since this is a Fixed Duration task,
I need to change the duration to 253d instead of 316d to bring the Task
finish back to 6/25/10 to match the resource assignments finish. The task
has NO constraints (ASAP).
The task has an Actual Start, so the predecessor is not driving it. There
is NO Actual Finish and it is showing as 20% complete. The last actual work
was as of 10/2/09.
I've tried changing the Finish date instead of the duration and it won't let
me change that either.
Any suggestions as to what is causing this?
Finish that is showing 3 months late. When I try to change the duration from
316d to 253d, it will not change.
All the resource assignments for this task are showing a Finish of 6/25/10,
but the Task Finish is showing 9/24/10. Since this is a Fixed Duration task,
I need to change the duration to 253d instead of 316d to bring the Task
finish back to 6/25/10 to match the resource assignments finish. The task
has NO constraints (ASAP).
The task has an Actual Start, so the predecessor is not driving it. There
is NO Actual Finish and it is showing as 20% complete. The last actual work
was as of 10/2/09.
I've tried changing the Finish date instead of the duration and it won't let
me change that either.
Any suggestions as to what is causing this?