create a calendar breaking the day into four periods & showing it

A

Andrew

I would like to create a calendar which splits the working day into four
sections - working 24 hours - I would then want to produce a programme over
that period with the vertical lines showing the four phase split. Any help
would be appreciated.

Andrew
 
R

Rod Gill

Firstly all shifts must start and finish on the same day. Secondly the only
vertical lines you can get automatically are those available under Format,
Timescale so I don't think you can do what you want.

Sorry!
 
D

davegb

Rod said:
Firstly all shifts must start and finish on the same day.

I think you mistated that, Rod, or I misinterpreted it. A shift can
start at, say 11pm and end at 7am the next day.
 
M

Mike Glen

I think he meant that shifts must be DEFINED individually within the same
day: ie midnight to 7am and 11pm to midnight for that 8-hour shift.

Mike Glen
Project MVP
 