Hello, it seems I cannot create split tasks with the PSI. Is this right?
G Gary L. Chefetz Nov 4, 2008 #2 Makkan: If you don't get a reply here, you might try microsoft.public.project.developer where development questions are asked and answered every day. -- ---------- Gary L. Chefetz, MVP MSProjectExperts Project Server Consulting: http://www.msprojectexperts.com Project Server Training: http://www.projectservertraining.com Project Server FAQS: http://www.projectserverexperts.com Project Server Help Blog: http://www.projectserverhelp.com
Makkan: If you don't get a reply here, you might try microsoft.public.project.developer where development questions are asked and answered every day. -- ---------- Gary L. Chefetz, MVP MSProjectExperts Project Server Consulting: http://www.msprojectexperts.com Project Server Training: http://www.projectservertraining.com Project Server FAQS: http://www.projectserverexperts.com Project Server Help Blog: http://www.projectserverhelp.com
M Marc Soester [MVP] Nov 4, 2008 #3 Hi Makkan, there are some restrictions with the PSI ( e.g. Baselineing) and I believe you cant split a task wiht the PSI either. But in order to make sure that this is the case, you should post the question to the developer user group as suggested by Gary
Hi Makkan, there are some restrictions with the PSI ( e.g. Baselineing) and I believe you cant split a task wiht the PSI either. But in order to make sure that this is the case, you should post the question to the developer user group as suggested by Gary