Naomi --
Oh, no! I missed one word in my directions for you. Click Tools -
Customize - Enterprise Fields. Then you're in business. Many apologies for
my oversight!
--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultanthttp://
www.msprojectexperts.comhttp://www.projectserverexperts.com
"We wrote the book on Project Server"
Yes, I did just as you said. Only "fields" is grayed out.
On Jan 29, 10:31 am, "Dale Howard [MVP]"
<dale(dot)howard(at)msprojectexperts(dot)com> wrote:
Naomi --
Did you click Tools - Enterprise Options - Open Enterprise Global to get
the
Enterprise Global file open for editing? If not, you must. Let us know.
--
Dale A. Howard [MVP]
Enterprise Project
Trainer/Consultanthttp://
www.msprojectexperts.comhttp://www.projectserverexperts.com
"We wrote the book on Project Server"
message
Dale, of all the choices in E. Global, "fields" is grayed out. I have
all permissions. WHat could be the problem?
Naomi
On Jan 26, 7:31 pm, "Dale Howard [MVP]"
<dale(dot)howard(at)msprojectexperts(dot)com> wrote:
Naomi --
The column you seek, which is the Inactive column, is not available in
the
Resource Center view. Therefore, you must "trick" Project Server into
showing you the information you seek. Here's how:
1. Open the Enterprise Global for editing and then click Tools -
Customize - Fields.
2. Select the Resource option at the top of the dialog and then
select
the
first available Flag field, such as Flag1.
3. Rename the resource Flag1 field as "Is Inactive".
4. Add the following formula to the "Is Inactive" field: [Inactive]
5. Click the OK button to close the Customize Enterprise Fields
dialog.
6. Save and close the Enterprise Global file.
7. Exit and relaunch Microsoft Project Professional.
This first set of steps allows you to capture the value in the
Inactive
field in another field that you can add to the Resource Center view.
Next,
complete the following steps to activate the new field in the
Enterprise
Resourcr Pool:
1. Click Tools - Enterprise Options - Open Enterprise Resource Pool.
2. In the Open Enterprise Resources dialog, select the "Include
inactive
resources" option and then click the Apply Filter button.
3. Click the Select/Deselect All button and then click the Open/Add
button.
4. Press the F9 function key to calculate the new field and then save
and
close the Enterprise Resource Pool.
Now create your Resource Center view and include the new enterprise
resource
Flag1 (Is Inactive) field to the list of fields in the View. Apply
filtering or grouping as you desire, and remember to include the View
in
at
least one Category. After you save and then apply the View, you will
see
the Is Inactive field correctly populated with the information you
seek.
Hope this helps.
--
Dale A. Howard [MVP]
Enterprise Project
Trainer/Consultanthttp://
www.msprojectexperts.comhttp://www.projectserverexperts.com
"We wrote the book on Project Server"
message
Good day,
I am modifying a view within Resource Assignments. I'd like to
filter
by active/inactive resources but that field is not available. It is
available in the Resource Center views. It's really important that
I
be able to filter because we have a large staff half of whom are
listed
as inactive. Any thoughts?
Thanks,
Naomi- Hide quoted text -- Show quoted text -- Hide quoted text --
Show quoted text -- Hide quoted text -- Show quoted text -- Hide quoted text -- Show quoted text -- Hide quoted text -- Show quoted text -