M
Manish Patel
I am trying to create a link from one task to another with
a little twist, I guess. Basically, I have a task that
needs to be temporarily paused while another task must be
completed before it can be finished. So I split the first
task, but I cannot seem to link the "end" (where the split
begins) to the second task. I will also need to link the
end of the second task back to the "start" (where the
split ends) of the first task. I hope I'm not just
overlooking something, but I am stumped. Any suggestions?
a little twist, I guess. Basically, I have a task that
needs to be temporarily paused while another task must be
completed before it can be finished. So I split the first
task, but I cannot seem to link the "end" (where the split
begins) to the second task. I will also need to link the
end of the second task back to the "start" (where the
split ends) of the first task. I hope I'm not just
overlooking something, but I am stumped. Any suggestions?