Sorry still lost on the formula, unless you are refering to the
statement
that provides how to find the 100%
(??Select Field, then from the dropdown %Complte.
OK.
Now click graphical indicators
Equals 100 select the stoplight you want. ??)
I cannot figure out how to make the yelllow and red lights show for a
task
that might be late or is late. What is that criteria, and is it
located
in
the same place as the 100% is located?
Vicki
VIcki
:
Hi,
You could indeed insert columns for Actual Duration and Remaining
duration
but if you show the Tracking toolbar (can you do that, Tools,
Customize,
Toolbars) there is a button "Update Tasks"
Select the task you want to track, click the Update Tasks button: it
has
it
all for you. Actual duration, remaining duration, actual start.
As for the buttons, refer to my previous mail (still attached below).
Don't
worry about the fact the formula uses %complete: Project will
calculate
that
from actual and remaining duration.
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
Jan, sorry but this has confused me.
I got the baseline set.
But I do not follow the rest.
Do I need to add a column for Acutal Duration?
And if I do what is my criteria, to have the indicator stoplight
show
yellow
is not completed?
Vicki
:
Hi,
Can you compare 60% to April 17? I can't!
First, if you want to check finish dates vs. the original plan, you
should
set a baseline at the start of the project.
Tools, Tracking, Set baseline;
Lok at the Tracking Gantt; the grey half-bars represent the
baseline
and
they won't move when reality starts to move your plan.
Second, I personally do NOT use % complete, that's like in NOT.
In dact, %complete=actual duration (time tehre ha already been any
work
on
the ask/total duration.
Now you are asking for a formula to do the reverse... don't make
the
division in the first place, enter actual duration and remaining
duration
instead.
Tools, Tracking, Update tasks allows you to record progress on the
selected
task very accurately.
There is also a button "update tasks" on the Tracking Toolbar.
Hope this helps,
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
Yay, it was as easy as I thought that it should be! Thanks Jan.
Next question, how do I compare the %Complete to the finish date?
or
is
that the criteria? I need to show if the finish date is like 2
days
out
but
the %Complete is less than 50%.
Vicki
:
Hi,
The tests for graphical indicators only work on the value in the
field
itself
To change that value you need a formula
So for instance:
Tools, Customize, Fields, select Number1
Click the word Formula
Select Field, then from the dropdown %Complte.
OK.
Now click grahical indicators
Equals 100 select the stoplight you want.
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
Hi, well I must be the idiot on the block because the set of
instructions
that Dale gave to Dan does not work for me. I have project
2000,
I
know,
anyway, I followed the instructions to get this step
completed:
"Select
the
"Task" set of fields, select Duration as the field Type, and
select
the
Enterprise Duration1 field" thru to adding in the Tests and
values.
I
have
green lights everywhere.

But as I move to the next step:
"To
create
the Finish Variance stoplight indicators, the Project Server
administrator
must also create a custom enterprise Project field by
completing
the
following steps" I get lost. I do not have a Projects set of
fields
and I
do
not have the option (or at least cannot find it) to "Import
Customer
field".
I do not want to use baseline or such.
Acutally while I am asking I would rather have my indicators
work
off
of
the
% Complete field and test something like IIf [%Complete] = 100
then
show a
black light (if I add this in as a formula I can't get past
the
test)
and
then add in the finish date, as in IIf [%Complete] < 100 AND
<> 0
AND
[Finish
Date] > "Current date" by (need help here too) 2 weeks then
show
Green
light.
Help?
:
Dan --
Refer to the following FAQ for an example of how to do it:
http://www.projectserverexperts.com/Shared Documents/CreateStoplightIndicators.htm
If you are not using Project Server with Microsoft Project,
then
simply
ignore the Project Server content. Hope this helps.
Can someone help an idiot create a column which shows a
status
light
of
a
task?
I presume it would be a calculated field that displays the
"red,
Yellow
or
Green stoplight" in a column in Project, but cannot figure
out
for
the
life
of me how to do it.
I'd appreciate any direction.
Dan