J.Allman
I have a question regarding the statusing of a project using EV.
Specifically, I am trying to create a series of green/yellow/red lights in a
new column to reflect when individual tasks in the project start to fall
behind on total work performed per task over the duration of the project.
My current formula is:
IIf([Work]=0 And [Baseline Work]=0,11,IIf([Work]=0 And [Baseline
Work]>0,10,IIf([Actual Work]=0 And [SV%]=0,0,IIf([% Complete]=100 And [Finish
Variance]>0,5,IIf([% Complete]=100 And [Finish
Variance]<=0,2,IIf([SV%]>-10,1,IIf([SV%]>-20,3,IIf([SV%]<=-20,8))))))))
The majority of the formula is tracking other events that happen in the
project but the part of the formula that focuses on the
green(1)/yellow(3)/red lights(8) are:
,IIf([SV%]>-10,1,IIf([SV%]>-20,3,IIf([SV%]<=-20,8))))))))
My problem occurs when I have a task that is currently being worked that has
a <baseline work> of 20 hrs a <work> of 20 hrs and an <actual work> of 18
hours..in this scenario the light is yellow as it falls between that 10% -
20% behind schedule.
HOWEVER, this task has baseline start and finish dates that should have
occured 6 weeks ago. This task even has a start date that occured 4 weeks ago
and the resource has not been working the task quickly.
I also have tasks similar to this one that are green because the actual work
is almost 100% complete even though the task is running 2 months behind
baseline schedule.
Does this have something to do with unfinished predecessors?
Should there always be a status date assigned or can it be left at NA?
Why is this happening?
Specifically, I am trying to create a series of green/yellow/red lights in a
new column to reflect when individual tasks in the project start to fall
behind on total work performed per task over the duration of the project.
My current formula is:
IIf([Work]=0 And [Baseline Work]=0,11,IIf([Work]=0 And [Baseline
Work]>0,10,IIf([Actual Work]=0 And [SV%]=0,0,IIf([% Complete]=100 And [Finish
Variance]>0,5,IIf([% Complete]=100 And [Finish
Variance]<=0,2,IIf([SV%]>-10,1,IIf([SV%]>-20,3,IIf([SV%]<=-20,8))))))))
The majority of the formula is tracking other events that happen in the
project but the part of the formula that focuses on the
green(1)/yellow(3)/red lights(8) are:
,IIf([SV%]>-10,1,IIf([SV%]>-20,3,IIf([SV%]<=-20,8))))))))
My problem occurs when I have a task that is currently being worked that has
a <baseline work> of 20 hrs a <work> of 20 hrs and an <actual work> of 18
hours..in this scenario the light is yellow as it falls between that 10% -
20% behind schedule.
HOWEVER, this task has baseline start and finish dates that should have
occured 6 weeks ago. This task even has a start date that occured 4 weeks ago
and the resource has not been working the task quickly.
I also have tasks similar to this one that are green because the actual work
is almost 100% complete even though the task is running 2 months behind
baseline schedule.
Does this have something to do with unfinished predecessors?
Should there always be a status date assigned or can it be left at NA?
Why is this happening?