H
hayansekki724
I'm trying to create a relative time constraint in project, but I can't
seem to find any option other than entering a fixed date. Example
below.
I want task 2 to start no earlier than two weeks after task 1
completes, and I want task 2 to complete no earlier than four weeks
after task 1 completes. I don't want to enter the actual value of ([task
1 complete date]+[2 weeks]) for my start date, because task 1 will have
an end date that is variable.
Can anyone tell me how I could get Project (2007) to accept a formula
for the date restrictions?
Thanks in advance!
seem to find any option other than entering a fixed date. Example
below.
I want task 2 to start no earlier than two weeks after task 1
completes, and I want task 2 to complete no earlier than four weeks
after task 1 completes. I don't want to enter the actual value of ([task
1 complete date]+[2 weeks]) for my start date, because task 1 will have
an end date that is variable.
Can anyone tell me how I could get Project (2007) to accept a formula
for the date restrictions?
Thanks in advance!