Creating relative date restrictions

H

hayansekki724

I'm trying to create a relative time constraint in project, but I can't
seem to find any option other than entering a fixed date. Example
below.

I want task 2 to start no earlier than two weeks after task 1
completes, and I want task 2 to complete no earlier than four weeks
after task 1 completes. I don't want to enter the actual value of ([task
1 complete date]+[2 weeks]) for my start date, because task 1 will have
an end date that is variable.
Can anyone tell me how I could get Project (2007) to accept a formula
for the date restrictions?

Thanks in advance!
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top