Critical Path Caluculation

R

RD

I have a project in "Ready" mode, where non-critical tasks show 0 days of
Total Slack even though they have Total Slack greater than 0. Once F9 is
selected, the correct Total Slack values display. Calculation mode is set to
Automatic. If "Calculate" mode was enabled, I would understand the need for
an F9.

I have witnessed other calcualtion issues with Project 2003 that require
something like a change in views to solve the calcualtion issue(s).
 