B
BigFish311
I am currently using MS Project 2000 and having issues calculating the
critical path through 3 different schedules. When I open up the total slack
column and starting tracing it manually backward I see a change in the total
slack value when the link crosses from one project to another. On a couple
of the links that I see the change in slack they have around 30 days of lag
on them. First off, that big chunk of lag is not my decision to use, but
when that amount of lag goes over a holiday break should that change the
number in the slack field because I sometimes can count the holidays and that
same amount is the change in slack? These changes in slack are sometimes
negative and I have no deadlines, must start, or must finish constraints set.
I appreciate any help on this issue. Thanks.
critical path through 3 different schedules. When I open up the total slack
column and starting tracing it manually backward I see a change in the total
slack value when the link crosses from one project to another. On a couple
of the links that I see the change in slack they have around 30 days of lag
on them. First off, that big chunk of lag is not my decision to use, but
when that amount of lag goes over a holiday break should that change the
number in the slack field because I sometimes can count the holidays and that
same amount is the change in slack? These changes in slack are sometimes
negative and I have no deadlines, must start, or must finish constraints set.
I appreciate any help on this issue. Thanks.