L
lk50
Hi there,
What is the best practice in using critical path analysis and how i
this done in Ms Project?
My understanding is that:
You determine what the end date of the schedule you want it to be b
adding a must finish on contstraint on the final date.
In the total slack column any task that is 0 or below is then on th
critical path.
Is that all there is to it or am I missing something??
Many thank
What is the best practice in using critical path analysis and how i
this done in Ms Project?
My understanding is that:
You determine what the end date of the schedule you want it to be b
adding a must finish on contstraint on the final date.
In the total slack column any task that is 0 or below is then on th
critical path.
Is that all there is to it or am I missing something??
Many thank