N
NH Ralph
We work with large, complex networks. Does anyone know of a tool or
technique which will allow you to efficiently analyze and crash the critical
path? i.e. If we wish to reduce our schedule duration, we can use total
slack, but it does not necessarily tell you the impact reducing an activity
duration may have on the total schedule. So if I have a 25 day task
currently on the critical path, reducing the duration to 10 days may only
yield a total schedule duration reduction of 5 days. But a similar reduction
on a 15 day task on the critical path may yield a greater total schedule
savings. Any suggestions to efficiently capture the high impact activities?
technique which will allow you to efficiently analyze and crash the critical
path? i.e. If we wish to reduce our schedule duration, we can use total
slack, but it does not necessarily tell you the impact reducing an activity
duration may have on the total schedule. So if I have a 25 day task
currently on the critical path, reducing the duration to 10 days may only
yield a total schedule duration reduction of 5 days. But a similar reduction
on a 15 day task on the critical path may yield a greater total schedule
savings. Any suggestions to efficiently capture the high impact activities?