A
Armand451
Hello all,
I have a question on how to show the critical path on a project constructed
with a specific end date. I know how to show all tasks that are technically
critical (defined in my Project by activities that have five or less days of
float), but I do not know how to show the thread from start to finish that
has the least amount of float. Because too many of the activities have more
than five days of float built into them. The schedule was not designed by
using the textbook method of creating activities, estimating their times,
sequencing them, and then determining relationships. So we have a good amount
of float in total, but I still want to be able to show with a click the
Critical Path.
Thanks in advance!
Jordan
I have a question on how to show the critical path on a project constructed
with a specific end date. I know how to show all tasks that are technically
critical (defined in my Project by activities that have five or less days of
float), but I do not know how to show the thread from start to finish that
has the least amount of float. Because too many of the activities have more
than five days of float built into them. The schedule was not designed by
using the textbook method of creating activities, estimating their times,
sequencing them, and then determining relationships. So we have a good amount
of float in total, but I still want to be able to show with a click the
Critical Path.
Thanks in advance!
Jordan