Hi, appreciated if you can help on below matter...

My boss created a project plan template for other
colleagues. When I created a new project plan by the
template and then enabling the tracking Gantt view, it's
found there are some red line (critical) tasks. I am
wondering why it will happen. I expect only blue line for
a project plan starting. How to resolve it?
 
M

Mike Glen

Hi Vincent,

Welcome to this Microsoft Project newsgroup :)

If a project has only one task, it is critical. Every project has a
critical path joining the critical tasks. Thus you will always have
critical tasks and they default to a red bar in the Tracking Gantt view. In
the Gantt Chart view, you need to run the Gantt Chart Wizard to turn
critical bars red. If you're unsure of how criticality is calculated, have
a look at FAQ Item: 42. Guide to Network Analysis.

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :)

Next time, try posting on the project newsgroup, as this one is closing
down! Please see FAQ Item: 24. Project Newsgroups.

Mike Glen
Project MVP


Mike Glen
Project MVP
 
Top