Cross Project Dependency

R

Ripper

I have set up a Program level schedule with multiple cross project
dependencies to lower level projects. In one specific case, I had multiple
tasks linking to 3 tasks in the program schedule. When I open the lower
level schedule I see the linked tasks from the program for 2 of the tasks but
not the third.
Any ideas as to why all 3 don't show up?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top