CURRENT Resource Availability using Portfiolo Analyser

C

Chris Walsh

I am trying to design a report on Current Availability of all resources across all projects, but when i add the 'Availability' column into the view all values are the same, even though most of the resources are being used at 85%!!

What is the go??
 
E

Ellen

Availability is the total hours that a resource has that
could be consummed by task assigments. It sounds like you
want the difference between Availability and Actual Work
or Baseline Hours.

Use the Pivot Table help for information on creating
calculated fields in PA views.

Hope this helps

Ellen
-----Original Message-----
I am trying to design a report on Current Availability of
all resources across all projects, but when i add
the 'Availability' column into the view all values are the
same, even though most of the resources are being used at
85%!!
 