Dear all,
at the beginning I created 5 calendar, from 1 day per week to 5 days per
week, to match each chance, actually I need to delete 4 of them cause
internal changes, when I try to delete them from The Enterprise Calendars
link in Server settings (Project Server 2007, sorry
) I receive an error
saying "The calendar is in use by the following projects: xxxx xxxx xxxx xxxx
xxxx ..... Edit the projects to use a different calendar and try again."
Checking each project, calenadar that I chose to delete are not used in
project information nor on each resource on the project, the only thing is
that tasks are not tied to any calendar.
Someone had this problem and solved it?
Thank you again.
Matteo
at the beginning I created 5 calendar, from 1 day per week to 5 days per
week, to match each chance, actually I need to delete 4 of them cause
internal changes, when I try to delete them from The Enterprise Calendars
link in Server settings (Project Server 2007, sorry
saying "The calendar is in use by the following projects: xxxx xxxx xxxx xxxx
xxxx ..... Edit the projects to use a different calendar and try again."
Checking each project, calenadar that I chose to delete are not used in
project information nor on each resource on the project, the only thing is
that tasks are not tied to any calendar.
Someone had this problem and solved it?
Thank you again.
Matteo