Custom Calendar

J

JMZ

How do I create a calendar based off our accouting month end days instead of
the standard calendar dates?
Meaning, I'd like for the month of January to be from December 19 thru Jan27.
February to be from Jan 29 to Feb 3 and so on through December.
Please advise,
JMZ
 
M

Mike Glen

Hi JMZ,

Welcome to this Microsoft Project newsgroup :)

There's no way to set this up within Project. Remember that Project is a
scheduelling program and not an accounting package. However, you can always
extract data between specified dates for use by the accountants.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 
C

Catfish Hunter

Look at Tools/Options/Calendar and see if that helps. You can set the start
of a year there then go to tools chage working time and look at the Standard
calendar there. It should say (Project Calendar) next to it. Good Luck
 