I have a template that was created by a former employee
that has columns called Orig. Est., Current Est. and
Remaining. I think he just renamed the "remaining work"
column to be "remaining." How about the orig and current
estimate columns? I want to use these columns in a new
project plan that was already created using a different
template.

Thanks for your help,
Tara
 
G

Gary L. Chefetz \(MVP\)

Tara:

It sounds like the previous person simply added a label to existing fields
as follows:

baseline work = Orig. Est.
work = Current Est


--

Gary L. Chefetz, MVP
"We wrote the book on Project Server
http://www.msprojectexperts.com

-
 