custom field in task usage view

R

Riko Wichmann

Hi everyone,

I created a custom field, say to calculate costs for personnel out of
the "work" field in MS Project. For a certain project report or
analysis, I use the "task usage" view, so that I can see for every
outline level 1 task what costs occur in defined time slices.

Unfortunately, not all all numbers I would like to see can be selected
for the view. By right click and selecting "Detail Styles ..." I can
add pre-defined fields to the view, but not the custom fields.
Is there any way to add also custom fields to this list, so that they
can be displayed in the task usage?

Any hint would me greatly appreciated.

Cheers,

Riko
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top