Custom Fields in MSProject Can I limit their use to one instance??

B

Brad Harris

MSP2K7
We have crated an Enterprise Custom Field that we can insert into our
Projects and have created a drop down list for the PM to select from however
once they chose a selection from the drop down list, we want to restrict that
particular selection from being used anywhere else in the project. How can I
do this? Said another way in a simple scenario, If I insert a enterprise
custom column called COLOR into my project and select a choice from the drop
down list called RED, I do not want RED to be a valid choice anymore. ONLY
one red allowed in the project.
 
P

Paul Conroy

You could achieve this with macro which queries the same field for other
tasks. Depending on the size of your projects this could prove to be
cumbersome/timely.

I can't think of an alterntive method.

P
 
J

Jack Dahlgren

As Paul states, there is no built-in function to restrict choices like this.
I don't think that a macro would be a suitable option either.

-Jack Dahlgren
 