I commonly utilise the "Task Entry" view when entering and reviewing tasks
and their resources, predecessors and successors. I know that there are a
number of views available in this "view" including resources & predecessors,
resources & predecessors, and predecessors & successors.



However, there seems to be sufficient space to add an additional table to
this form view so that resources, predecessors and successors could all be
visible at once. I don't know about anyone else but I would find this
layout extremely useful and the absence of this option seems to be an
obvious oversight.



Can anyone advise me if it is possible to customise this form/view and if so
how do I go about it?



Thanks



Jack
 
G

Gérard Ducouret

Hello Jack,

Sorry, the task form, and the Resource Form too, is not customizable



Gérard Ducouret
 
D

davegb

However, while you can't add an addtional table to the split screen
view at the bottom, you can add an addtional column in the table up in
the Entry View/Entry Table to display resources, and you can modify the
Gantt to show resources, or predecessors and/or successors next to the
Gantt bars, and be able to see Resources, Predecessors and Successors
all at the same time.
 