Customize gantt chart

M

MP

Is it possible to create a view with a gantt chart where I can compare the
actual situation of a project with a baseline 1 to 9 (instead of baseline 0
already avaiable in the tracking view?)

(I'm using PS2007)

Thanks in advance,
MP
 
J

Jan De Messemaeker

Hi,

Yes.
View Menu, More Views
Sellect Tracking Gantt, Click Copy
Give the copy a new name f.i. Tracking1 Gantt
Gat out of the menus, activate tracking1 Gantt
Format, Bar Styles
Look at the columns From and To
Everywhere you see Baseline replace by Baseline1

There you are.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
M

MP

Thanks a lot. Very helpful!

Jan De Messemaeker said:
Hi,

Yes.
View Menu, More Views
Sellect Tracking Gantt, Click Copy
Give the copy a new name f.i. Tracking1 Gantt
Gat out of the menus, activate tracking1 Gantt
Format, Bar Styles
Look at the columns From and To
Everywhere you see Baseline replace by Baseline1

There you are.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
Top