P
Pat
I am looking for information about each of the available Methods for
Reporting Progress in the Customize Published Fields. I have found
the basic definitions about what each option will provide but that is
not enough. I am looking for the recommended options based on the
level of detail and needs for the Project Manager and Business.
For example:
Reporting % Complete - makes sense to use this if your level of
Project Management is low. Simply depicting project progress and
little else.
Actual Work Done - Provides more detail on assignments as to the
actual amount of time spent. However, actual start & finish dates are
not always accurate.
Work done per Time Period - provides a greater amount of detail and
accuracy on assignments as to actual amount of time spent and when
this time actually occured.
The big questions come into play when you want to take Project
Management and the EPM tool to a further degree - Earned Value
reporting, Forecasting and Resource Allocations. How do these options
affect these more advanced capabilities offered by the EPM solution?
Which option should I use and in what Situations?
Pat
Reporting Progress in the Customize Published Fields. I have found
the basic definitions about what each option will provide but that is
not enough. I am looking for the recommended options based on the
level of detail and needs for the Project Manager and Business.
For example:
Reporting % Complete - makes sense to use this if your level of
Project Management is low. Simply depicting project progress and
little else.
Actual Work Done - Provides more detail on assignments as to the
actual amount of time spent. However, actual start & finish dates are
not always accurate.
Work done per Time Period - provides a greater amount of detail and
accuracy on assignments as to actual amount of time spent and when
this time actually occured.
The big questions come into play when you want to take Project
Management and the EPM tool to a further degree - Earned Value
reporting, Forecasting and Resource Allocations. How do these options
affect these more advanced capabilities offered by the EPM solution?
Which option should I use and in what Situations?
Pat