customize timesheet in PWA

M

Mario

Hi,

Is it possible to customize the timesheet in PWA? I would
like to remove a column for all user but I don't know how
to do that. Is it possible?

Thanks,
Mario
 
S

Sarah

Mario,
Do you know if it's possible in the timesheet to show task
name under the project name. At this time, the task name
is under % complete and I would like to change this. Do
you know if it's possible?

It sounds like you have it grouped by % Complete, then by Task Name.
Change it to be grouped by Project, then by Task Name. This is
something each user must do on their own view.

Sarah
 