Customizing the Gantt timescale

A

Andy Stewart

In our company, we use a work week calendar that numbers
the weeks in a year. Sometimes workweek #1 starts the
last week in December. So I would like to be able to
control the gantt timescale, such that it displays the
label on the weeks according to the way our company
calculates the workweek number. Is there a way for me to
do that using VBA?
 
J

Jack D.

Andy said:
In our company, we use a work week calendar that numbers
the weeks in a year. Sometimes workweek #1 starts the
last week in December. So I would like to be able to
control the gantt timescale, such that it displays the
label on the weeks according to the way our company
calculates the workweek number. Is there a way for me to
do that using VBA?

Answered in private mail.

--
Please try to keep replies in this group. I do check e-mail, but only
infrequently. For Macros and other things check http://masamiki.com/project

-Jack Dahlgren, Project MVP


+++++++++++++++++++
 
C

Curtis

This sounds very interesting, anyway I can get this
information from Jack?


Thanks
Curtis
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top