B
BillinMN
I need to create report that displays the daily time entered for each task
for each resource. What tables do I need to pull together?
for each resource. What tables do I need to pull together?
Steven Yetter said:See the Report Hours worked for a resource during a period by project thread
but the SQL below did the trick for me.
SELECT
TOP 100 PERCENT p.PROJ_NAME, r.RES_NAME, a.TASK_NAME, a.ASSN_ACT_WORK /
60000 AS actual_hours, a.ASSN_START_DATE AS start_date,
a.ASSN_FINISH_DATE AS finish_date, a.ASSN_WORK / 60000 AS assigned_work,
a.ASSN_REM_WORK / 60000 AS remaining_work,
a.WASSN_LAST_WORK / 60000 AS assigned_last_work, a.WASSN_SEND_UPDATE_DATE AS
update_sent_date,
(w.wwork_value * (DATEDIFF(day, w.WWORK_START, w.WWORK_FINISH)+1 ))/60000 as
[work],
w.WWORK_START as work_start, w.WWORK_FINISH as work_finish
FROM MHCCSCP1.ProjectServer.dbo.MSP_WEB_RESOURCES r INNER JOIN
MHCCSCP1.ProjectServer.dbo.MSP_WEB_ASSIGNMENTS a ON
a.WRES_ID = r.WRES_ID INNER JOIN
MHCCSCP1.ProjectServer.dbo.MSP_WEB_PROJECTS p ON
p.WPROJ_ID = a.WPROJ_ID INNER JOIN
MHCCSCP1.ProjectServer.dbo.MSP_WEB_WORK w on
a.WASSN_ID = w.WASSN_ID
WHERE w.wwork_type = 1 and w.wwork_value > 0
ORDER BY w.WWORK_START, p.PROJ_NAME, r.RES_NAME, a.TASK_NAME
Gérard Ducouret said:Hello Billin,
Have you tried the "Task Usage" view with the "Work" field:
View / Task Usage
NB : you can add some other fields : right Click a yellow cell...
Hope this helps,
Gérard Ducouret
BillinMN said:Thanks!! That query runs jsut fine. How would I include the summary tasks
that the lowlevel tasks are associated to?
Steven Yetter said:See the Report Hours worked for a resource during a period by project thread
but the SQL below did the trick for me.
SELECT
TOP 100 PERCENT p.PROJ_NAME, r.RES_NAME, a.TASK_NAME, a.ASSN_ACT_WORK /
60000 AS actual_hours, a.ASSN_START_DATE AS start_date,
a.ASSN_FINISH_DATE AS finish_date, a.ASSN_WORK / 60000 AS assigned_work,
a.ASSN_REM_WORK / 60000 AS remaining_work,
a.WASSN_LAST_WORK / 60000 AS assigned_last_work, a.WASSN_SEND_UPDATE_DATE AS
update_sent_date,
(w.wwork_value * (DATEDIFF(day, w.WWORK_START, w.WWORK_FINISH)+1 ))/60000 as
[work],
w.WWORK_START as work_start, w.WWORK_FINISH as work_finish
FROM MHCCSCP1.ProjectServer.dbo.MSP_WEB_RESOURCES r INNER JOIN
MHCCSCP1.ProjectServer.dbo.MSP_WEB_ASSIGNMENTS a ON
a.WRES_ID = r.WRES_ID INNER JOIN
MHCCSCP1.ProjectServer.dbo.MSP_WEB_PROJECTS p ON
p.WPROJ_ID = a.WPROJ_ID INNER JOIN
MHCCSCP1.ProjectServer.dbo.MSP_WEB_WORK w on
a.WASSN_ID = w.WASSN_ID
WHERE w.wwork_type = 1 and w.wwork_value > 0
ORDER BY w.WWORK_START, p.PROJ_NAME, r.RES_NAME, a.TASK_NAME
eachGérard Ducouret said:Hello Billin,
Have you tried the "Task Usage" view with the "Work" field:
View / Task Usage
NB : you can add some other fields : right Click a yellow cell...
Hope this helps,
Gérard Ducouret
"BillinMN" <[email protected]> a écrit dans le message de
I need to create report that displays the daily time entered for
taskfor each resource. What tables do I need to pull together?