Daily Work %

R

Ryan

I want my developers to be able to check their daily suggested/required work
amounts (%) to be shown on their tasks in Project Web Access, under the Tast
View. It doesnt appear, is there anyway to add this?

Ryan
 
D

Dale Howard [MVP]

Ryan --

There's no way to see this in the PWA timesheet view. There's no way for
them to know what percentage they should have completed on any particular
day. All they can do is enter they actual % Work Complete. Hope this
helps.
 