when entering the Time filed in the Data Analysis the years start early as
1984 and ends some where in 2100, Why is it ?
Can you configure the time period start and finish years ?

Thanx
 
J

JulieS

Hello shoham,

From help topic Project Specifications:

The earliest date allowed for calculation is January 1, 1984
The latest date allowed for calculation December 31, 2049.

Dates earlier than 1984 and later than 2049 are not possible to the best
of my knowledge.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 