S
Swilly
I have a need to update a simple MS project schedule. The raw data
comes to me in the form of an XL spreadsheet. Let's just say that I
have 4 cols of data as follows
ID
Task Name
Finish Date
Text
All the tasks are milestones with 0 duration.
I will get a new file every day with revised finish dates. This would
OK if the number of lines were small but it over 500 line items. The
tasks do not change.
I would like to update MS project with the new finish dates. Cutting
and pasting will work but there are other reasons why I would prefer to
upload/import or pull in the data using a database or other feature in
project. Has anyone done this?
Thanks
Bill
comes to me in the form of an XL spreadsheet. Let's just say that I
have 4 cols of data as follows
ID
Task Name
Finish Date
Text
All the tasks are milestones with 0 duration.
I will get a new file every day with revised finish dates. This would
OK if the number of lines were small but it over 500 line items. The
tasks do not change.
I would like to update MS project with the new finish dates. Cutting
and pasting will work but there are other reasons why I would prefer to
upload/import or pull in the data using a database or other feature in
project. Has anyone done this?
Thanks
Bill