date 1 field # sign shows

B

bttyaywnf

When I input certain dates in MS Project, the # symbol shows up, even when
the dates are within the constraints. What am I doing wrong?
 
J

Jack Dahlgren MVP

Make the column wider by double clicking on the column header divider.
######## is displayed when the column is too narrow to show the whole date.

-Jack Dahlgren
 