Date calculations

F

Finsalgal

I am trying to get my form to work out start dates and end dates but i want
it to work on working days only ie MONDAY TO FRIDAY. So if i make a product
on A Monday and it takes till the following monday i want it to give me the
result 6 days i do not want it to calculate the weekend.

Kind regards
 
R

RuralGuy

I am trying to get my form to work out start dates and end dates but i
want it to work on working days only ie MONDAY TO FRIDAY. So if i make
a product on A Monday and it takes till the following monday i want it
to give me the result 6 days i do not want it to calculate the
weekend.

Kind regards

Hi,

Have you looked here yet?

http://www.mvps.org/access/datetime/date0006.htm
Date/Time: Calculate Number of Working Days

HTH
 
Top