Here's a stumper for me...

I have a colleague who is supporting another client in a different state.
In their version of MS Project Pro, they cannot get the date format to appear
as mm/dd/yy. Their versions only contain dd/mm/yy (and variations of that).


When I go to Tools/Options/View Tab/ Date format, I can see the one they
want - yet they cannot?!?!

Anyone have any idea why this is happening or what we can do to change their
configuration?
 
R

Rod Gill

Project Pro uses the date format set up in Regional Settings. For some
reason your colleague's PC probably has its location set up to be somewhere
in the world other than north America! Get to regional settings via the
Control Panel and reset it to USA

--

Rod Gill
Project MVP

Project VBA Book, for details visit:
http://www.projectvbabook.com

NEW!! Web based VBA training course delivered by me. For details visit:
http://projectservertraining.com/learning/index.aspx
 
R

RandyK

Hi Rod -

I had googled this situation and found exactly what you are referring to.
I sent an email to my colleague and hoping for the best! Thanks for the
reply to my post!
 