Date Format in PWA (MSP2007)

S

shoham

hi all,

I work with MSP 2007 server in the project pro the date format is dd/mm/yy
but in the PWA the format is mm/dd/yy I want it to be identical

How can I display the date format as dd/mm/yy in the PWA views?

Thanx
 
R

Rod Gill

In PWA Click on the Site Settings menu (near the top right of the screen).
There is a regional settings option or something similar there. In the same
place I usually set the Test instance color to red to make sure people
realise they are not in the production environment.

--

Rod Gill
Project MVP