Date format of Start and Finish dates

J

John Rutledge

Is there a way to change the format of the Start and Finish dates? We're
not so interested in the exact hours, so we'd like to just see the dates.

So, instead of
mm/dd/yyyy hh:mm AM
we only want
mm/dd/yyyy

Is that possible?
-- John Rutledge
 
D

Dale Howard

John -

I assume you are asking about changing the date format in PWA instead of
Project 2002. The format for the date fields in PWA can be changed on the
Tasks page by clicking the View Options tab and deselecting the "Show time
with date" option. The date format cannot be changed in either Project
Center or Project pages. The date format can be changed in the Resource
Center page or the View Assignments page by clicking the View Options tab
and deselecting the "Show time with date" option. Hope this helps.
 
Top