Hello

Someone already asked about this before but there was no answer about this
question, while I am facing the same issue right now.

In Project Profesional 2007, we can change the date format under Options,
because we are using date format dd/MM/yyyy

But come to server, the way we look it in pwa it's become MM/dd/yy

I was trying to change it to dd/MM/yyyy but no settings beside date option
for changing weekend etc.

If anyone know how to change date format in pwa, please let me know how

Regards

Rian Wisandanu
 
B

Ben Howard

Hi Rian,
From memory, you have to do this in the WSS settings and change the regional
settings.
 