Date missing in Portfolion Analyzer

A

Andrea

Hi,

we have problems with our Portfolio Analyzer. I have created a new project
with assignments and I have republished the project. Then, I rebuild the
cube and after the cube is completly built I go in Resource Portfolio
Analyzer and when I look a resource assigned to the project I have just
created, the work hours are equal to 0 and in the project it is 500 hours of
work.

It appears that there is a problem with the new project I have created
because when I modify projects that already exist, all the changes are
reflected in the portfolio analyzer.

Do you have any idea?
Thanks
 